Bagshaw Street Upgrades Project
Construction on the Bagshaw upgrades project is now complete. The water, sanitary, and storm sewer utilities have replaced the ditches and old asbestos-concrete pipes. Curbs and narrower travel lanes with street parking provide passive traffic calming, discouraging speeding and large-vehicle traffic. The new sidewalks and street trees allow a more comfortable experience for pedestrians and people using mobility devices.
Construction on the Bagshaw upgrades project is now complete. The water, sanitary, and storm sewer utilities have replaced the ditches and old asbestos-concrete pipes. Curbs and narrower travel lanes with street parking provide passive traffic calming, discouraging speeding and large-vehicle traffic. The new sidewalks and street trees allow a more comfortable experience for pedestrians and people using mobility devices.
-
Bagshaw Street Upgrades Update
August 25, 2021
After working on the underground storm and water utilities over summer, the contractor is starting surface works, including curbs, sidewalks, and landscaping on Bagshaw Street from Stanford Avenue East to the Island Highway East. New streetlights will accompany these surface works as the project nears completion in October. The project team is excited to facilitate an improved pedestrian and driver experience for later this year. -
Bagshaw Street Upgrades Update
December 21, 2020
Expected completion summer 2021
Following engagement with businesses and residents on Bagshaw Street during summer 2020, the City has selected a streetscape configuration responsive to feedback. The selected design will provide passive traffic calming, an improved pedestrian experience and street parking. A summary of ‘what we heard’ during public engagement as well as information about the ultimate design for Bagshaw Street and how this design is responsive to the community’s needs are provided below. Tendering is anticipated in early
Lifecycle
-
May - June 2020
Bagshaw Street Upgrades Project has finished this stageAnalysis and Concept Development
- Surface and sanitary sewer condition assessment
- Topography survey
- Background review
- Concept Development
-
July - August 2020
Bagshaw Street Upgrades Project has finished this stagePublic Engagement
- Survey
- Direct Outreach to impacted residents and businesses
-
September - November 2020
Bagshaw Street Upgrades Project has finished this stageFinalize Design
- Incorporate public input
- Third party utility coordination
- Detailed design package
- Permitting
-
January-March 2021
Bagshaw Street Upgrades Project has finished this stagePrepare for tender and construction
- Tender document preparation
- Communication with impacted residents and businesses
- Construction schedule to be determined
-
Finalize contract award and start construction
Bagshaw Street Upgrades Project has finished this stage- Finalize construction contract and award
- Notify all residents and businesses
- Start construction
-
Construction underway
Bagshaw Street Upgrades Project has finished this stage- Underground storm and water utilities completed over the summer
- Surface works, including curbs, sidewalks, and landscaping
-
Project complete
Bagshaw Street Upgrades Project is currently at this stage



